SCOPE OF WORK
Labor provided by Contractor
Unit#:170 Project: Mod/Ren
Segment: Parshall
Physical Address: 105 3rd ST NE
Kitchen – Labor Only
Install new base and wall cabinets
(Wall - 30x12, 30x12, 40x12 and 36x12)
(Base – 30x24, 36x24, 15x24, and 48x24)
Install new countertop, sink and faucet with sprayer
Install new range hood
Install new baseboard trim (60 LF)
Install new pantry door with doorknob (2-4 LH)
Install new closet door with doorknob (2-4 RH)
Install new basement door with doorknob (2-8 LH)
Install new refrigerator and stove
Install 2 floor vent covers (15x4)
Bedroom #1 – Labor Only
Install new bedroom door with privacy doorknob and door stop (2-6 RH)
Install new trim around doors and windows (90 LF)
Install new baseboard trim (60 LF)
Bedroom #2 – Labor Only
Install new door with privacy doorknob and door stop (2-6 LH)
Install new trim around doors and windows (90 LF)
Install new baseboard trim (60 LF)
Bedroom #3 – Labor Only
Install new bedroom door with privacy doorknob and door stop (2-6 RH)
Install new trim around doors and windows (90 LF)
Install new baseboard trim (60 LF)
Bedroom #4 – Labor Only
Install new bedroom door with privacy doorknob and door stop (2-6 RH)
Install new trim around doors and windows (90 LF)
Install new baseboard trim (60 LF)
Hallway – Labor Only
Install new wall vent cover (32x8)
Install new baseboard trim 50 (FT)
Bathroom – Labor Only
Install new toilet and supply lines
Install new vanity (24 inch) with faucet and supply lines
Install new shower tub combo with shower head and shower handle
Install new vanity mirror (24 in)
Install new toilet paper holder and towel holder
Install new bathroom door with privacy doorknob (2-4 LH)
Install new trim around windows and bathroom door (55 LF)
Install new baseboard trim (10 LF)
Whole Unit – Labor Only
Install new flooring throughout (1,160 Sq Ft)
Install 2,124 Sq Ft of 5/8” drywall
Install 1,830 Sq Ft of ½" drywall
Tape and texture
Paint and Primer 3,954 Sq Ft
Install new insulation throughout the house, including the attic.
Bids due January 30th 2025
Reminder: Dispose of all debris at an approved site. Clean the entire area around unit, this includes picking up all nails. Make sure the project is ready for final inspection